LOAD SHEDDING NEWS - With the increase in generation planned maintenance, as previously communicated and the loss of a further two generation units today, stage 6 load shedding will be implemented from 05:00 on Tuesday, 5 September until further notice.
You will be affected as follows:
GEORGE
- Monday 4 September: 22:00 - 00:30
- Tuesday 5 September: 04:00 - 06:30 | 12:00 - 16:30 | 20:00 - 00:30
- Wednesday 6 September: 04:00 - 06:30 | 12:00 - 14:30 | 20:00 - 00:30
UNIONDALE
- Monday 4 September: 17:00 - 21:30
- Tuesday 5 September: 07:00 - 09:30 | 15:00 - 19:30 | 23:00 - 03:30
- Wednesday 6 September: 07:00 - 09:30 | 15:00 - 17:30 | 23:00 - 03:30
SEDGEFIELD
- Monday 4 September: 22:00 - 00:30
- Tuesday 5 September: 04:00 - 06:30 | 12:00 - 16:30 | 20:00 - 00:30
- Wednesday 6 September: 04:00 - 06:30 | 12:00 - 14:30 | 20:00 - 00:30
KNYSNA | PLETTENBERG BAY
- Monday 4 September: 20:00 - 22:30
- Tuesday 5 September: 02:00 - 04:30 | 05:00 - 06:30 | 10:00 - 14:30 | 18:00 - 20:30
- Wednesday 6 September: 02:00 - 04:30 | 10:00 - 14:30 | 18:00 - 22:30
MOSSEL BAY
- Monday 4 September: 20:00 - 22:30
- Tuesday 5 September: 02:00 - 04:30 | 05:00 - 06:30 | 10:00 - 14:30 | 18:00 - 20:30
- Wednesday 6 September: 02:00 - 04:30 | 10:00 - 14:30 | 18:00 - 22:30
ALBERTINIA | RIVERSDALE | GOURITSMOND | STILBAAI | MELKHOUTFONTEIN | JONGENSFONTEIN
- Monday 4 September: 20:00 - 22:30
- Tuesday 5 September: 02:00 - 04:30 | 05:00 - 06:30 | 10:00 - 14:30 | 18:00 - 20:30
- Wednesday 6 September: 02:00 - 04:30 | 10:00 - 14:30 | 18:00 - 22:30
HEIDELBERG | SLANGRIVIER
- Monday 4 September: 18:00 - 20:30
- Tuesday 5 September: 00:00 - 02:30 | 08:00 - 12:30 | 16:00 - 20:30
- Wednesday 6 September: 00:00 - 02:30 | 08:00 - 10:30 | 16:00 - 20:30
OUDTSHOORN
- Monday 4 September: 20:00 - 22:30
- Tuesday 5 September: 02:00 - 06:30 | 10:00 - 12:30 | 18:00 - 20:30
- Wednesday 6 September: 02:00 - 06:30 | 10:00 - 14:30 | 18:00 - 20:30
GRAAFF-REINET
- Monday 4 September: 19:00 - 21:30
- Tuesday 5 September: 01:00 - 03:30 | 09:00 - 13:30 | 17:00 - 19:30
- Wednesday 6 September: 01:00 - 03:30 | 09:00 - 13:30 | 17:00 - 21:30
Consumers are urged to turn off high-usage equipment and where possible to not switch on appliances such as stoves and kettles for at least 30 minutes after load shedding.
This will reduce the risk of overload tripping on the network and reduce our current high MVA spikes.
Receive Eskom load shedding notifications by downloading the free EskomSePush app from Google Play Store at https://sepush.co.za/